Minister Tran Hong Minh: Accelerate progress on w88 luxury link w88 Khanh Hoa – Buon Ma Thuot expressway
(Construction) - During an inspection of w88 luxury link w88 Khanh Hoa – Buon Ma Thuot Expressway project, Minister Tran Hong Minh called on local authorities to promptly complete site handover procedures and urged contractors to accelerate construction progress.
On w88 luxury link w88 morning of 3rd April, Minister of Construction Tran Hong Minh visited w88 luxury link w88 site of Component 1 (DATP 1) of w88 luxury link w88 project to inspect compensation, site clearance and construction work.
![]() |
Inspecting w88 luxury link w88 Khanh Hoa – Buon Ma Thuot Expressway, Minister Tran Hong Minh noted significant improvements and positive developments at w88 luxury link w88 construction site. |
At w88 luxury link w88 intersection with w88 luxury link w88 Van Phong – Nha Trang Expressway, Minister Tran Hong Minh acknowledged w88 luxury link w88 efforts of w88 luxury link w88 investor and contractor in overcoming construction challenges and accelerating w88 luxury link w88 project progress. In particular, despite recent adverse weather conditions, w88 luxury link w88 site has shown marked improvement and encouraging progress.
With remaining site clearance issues along w88 luxury link w88 route causing interruptions to construction, Minister Tran Hong Minh urged Khanh Hoa Province to take decisive action in w88 luxury link w88 spirit of “for w88 luxury link w88 benefit of w88 luxury link w88 nation and w88 luxury link w88 people”, and to promptly clear w88 luxury link w88 site to open up access roads to w88 luxury link w88 project. He emphasised that this would create favourable conditions for w88 luxury link w88 contractor to complete w88 luxury link w88 works and help ensure w88 luxury link w88 expressway is brought into full operation.
Reporting to w88 luxury link w88 Minister, Director of Project Management Board 6, Tran Huu Hai (w88 luxury link w88 investor of w88 luxury link w88 Khanh Hoa - Buon Ma Thuot Expressway project) explained that, in addition to w88 luxury link w88 challenges posed by adverse weather and difficult ground conditions, w88 luxury link w88 project geology is complex. w88 luxury link w88 construction terrain of w88 luxury link w88 majority of w88 luxury link w88 main route from Khanh Hoa to Đak Lak passes through rugged mountains and forests, with forest land needing to be converted.
After listening to w88 luxury link w88 reports from w88 luxury link w88 units, Minister Tran Hong Minh instructed w88 luxury link w88 investor and contractor of Component Project 1 to make w88 luxury link w88 most of w88 luxury link w88 available land, develop a detailed construction plan, and arrange reasonable construction points to optimise each task. w88 luxury link w88 main focus should be on accelerating w88 luxury link w88 construction of bridges, roadbeds, and other key infrastructure.
w88 luxury link w88 construction units are to focus all resources, mobilise maximum human resources, equipment, and finances to organise construction, especially for w88 luxury link w88 critical path items of w88 luxury link w88 project. Work should proceed with w88 luxury link w88 spirit of "3 shifts, 4 teams" to ensure progress. Construction should begin immediately wherever w88 luxury link w88 site is ready. "We all recognise w88 luxury link w88 difficulties, but overcoming them to achieve remarkable results is what truly matters" w88 luxury link w88 Minister emphasised.
![]() |
Director of Project Management Board 6, Tran Huu Hai (front row, left), reports to w88 luxury link w88 Minister on w88 luxury link w88 progress of w88 luxury link w88 project. |
To complete w88 luxury link w88 20km section by w88 luxury link w88 end of 2025, as scheduled by w88 luxury link w88 Prime Minister, w88 luxury link w88 Project Management Board for Investment and Construction of Traffic Works in Khanh Hoa Province has recommended that w88 luxury link w88 People\'s Committee of Khanh Hoa direct w88 luxury link w88 People\'s Committee of Ninh Hoa Town to accelerate site clearance work. They also urged relevant agencies to coordinate with communes and wards to mobilise w88 luxury link w88 remaining households to hand over w88 luxury link w88 site to w88 luxury link w88 contractor for construction before 15th April.